Civil Engineering Projects planned for 2009 Print E-mail

Projects planned for 2010:

- The re-surfacing of the runway and aircraft parking area

- Civil works to comply with French Govt and EU water regulations

- Upgrading of all runway lighting and marking

- The installation of a simplified approach plus ramp to lower minima

- Construction of additional car parking spaces (3rd phase).


Temporary closure of the Airport for 12 weeks from January 2010


In order to proceed with the runway re-surfacing and the civil works to comply with water regulations, Deauville St-Gatien Airport will be closed for 12 weeks from the beginning of January 2010. The re-opening is planned for the first week of April 2010.

 
evden eve nakliyat evden eve nakliyat evden eve nakliyat evden eve nakliyat